Ricciardi Bros. Inc. will be starting the sewer pipe installation on the following days:  The tentative schedule and work description, subject to change,  as follows:

  • Monday (11/21) - Day time work in Uxbridge area (hours TBD). Starting at the Blackstone Valley Logistics Center warehouse entrance, installing 4-inch sewer force main along north side of Lackey Dam Road, ending prior to entering abeam MassDOT jurisdictional area at RT 146 northbound on-ramps.Tuesday (11/22) - Temporary trench patch on all open trenches from Monday's work.
  • Wednesday (11/23), Thursday (11/24) Thanksgiving, Friday (11/25) - No work in Uxbridge.
  • Sunday night (11/27) - Install 4-inch sewer force main across RT 146 northbound on-ramps.  Uxbridge - Since this is night work in a residential area, please advise the local residents of potential noise and lighting.
  • Monday (11/28) - No daytime pipe install work, as crews end at 5am from Sunday night.
  • Tuesday (11/29), Wednesday (11/30), Thursday (12/01), Friday (12/02) - Day time work in MassDOT jurisdictional area.  Install 4-inch sewer force main under both RT 146 bridges, from ramp to ramp.  Paving will occur at the beginning of each day for previous days opened trenches.
  • Sunday night (12/04) -  Install 4-inch sewer force main across RT 146 southbound off-ramps, possibly crossing Tennessee Gas Pipeline 
  • Monday (12/05) - No daytime pipe install work, as crews end at 5am from Sunday night. Temporary trench patch on all open trenches.
  • Tuesday (12/06), Wednesday (12/07) - Install 4-inch sewer force main in front of Shell gas station and Pyne entrance, ending at Uxbridge/Douglas town line.